HYPERSCALE DATA CENTRE I NORGE Trondheim 7 desember 2017 www.statkraftdatacentersites.com
Datasentre er en del av den digitale revolusjonen 2
En verden i endring Uber: Verdens største taxioperatør, uten kjøretøy Facebook: Verdens mest populære medieselskap, lager ikke noe innhold Alibaba: Airbnb: Verdens mest verdifulle utsalgssted, uten varer på lager Verdens største overnattingsaktør, eier ingen rom 3
Fokus på kraftkrevende hyperscale datasentre Enterprise datasenter - Vanligste type - <1 MW effekt Colocation datasenter - Tredjepartsadgang - 1-10 MW effekt Hyperscale datasenter - Google, Apple etc. - 10-240 MW effekt 4
GEVINSTER KNYTTET TIL ETABLERING DATASENTRE I NORGE 09.06.2017
KARAKTERISTIKA VED BYGGE- OG DRIFTSPERIODEN
ANTALL ÅRSVERK Sysselsettingseffekter over år
Virkninger av data sentre: Facebook s ketchupeffekt Facebook og mer i vente Facebook 1 (2011) & 2 (2013) Co-location data senter Hydro 66 Fortlax Datasentre for blockchain KnCMiner 2016: Datasenter industrien 7000 FTE Luleå universitet egne linjer og forskningsmiljø Telia Hoteller etc SICS Uavhengig forskningsmiljø Nytt regionhovedkontor 750 ansatt Stordalen investerer i tredje hotell i Luleå 8
Statkraft sin rolle >120 års samarbeide med kraftintensiv industri Hvordan det startet 9 Vindkraft på Fosen Vår tids industrielle revolusjon
Health and safety Caring for people is at the core of Statkraft s culture. A safe, secure and healthy working environment is paramount and this applies wherever we are. We work continuously to improve our performance towards our vision of zero injuries. 10
Hvorfor Norge er attraktivt Stabil og pålitelig tilgang på fornybar energi Lave kraftpriser Meget pålitelig strømnett Sterk politisk støtte både nasjonalt og regionalt Gunstig skatteregime for datasenter Politisk og økonomisk stabilitet Svært lav miljørisiko 11
Konkurransedyktige energipriser
Flere hyperscale datasentre i Norden Apple i Viborg Største utenlandske investeringen noensinne Amazon i Sverige Potensielt >1 USD MRD Facebook i Luleå 170 fast ansatte, store positive ringvirkninger Facebook i Odense 1.200 ansatte i byggefasen 184 mål under tak Google i Hamina >100 fast ansatte Samlet investering > 8,2 MRD NOK 13
Statkrafts rolle Statkraft tilrettelegger for Hyperscale datasentre for å redusere risiko og kostnad Statkraft Data senter investor Tomtevalg Tomteutvikling Finansiering Bygging Salg/Tilbakeleie Drift Screening Tomtevalg Få kontroll over tomt Tomteutvikling Pakketering, markedsføring og salg Opsjonsavtale Nettilknytning Fiber tilgang www.statkraftdatacentersites.com Tomte- og kommunebesøk Regulering og andre godkjenninger Kraftkjøpsavtaler og tjenester B2B markedsføring RFI er, DD, forhandlinger Statkraft kan følge prosjektet frem til normal drift 14
Statkrafts datasenterprosjekt; kjerneteamet Atle Haga Prosjektleder Ole Johan Lindaas Tomteutvikler Bjørn Holsen Prosjekteier Bjørn Drangsholt Forretningsutvikling Stian Bjørge Tomteutvikler Eivind Anders Sørlie Prosjektutvikler 15
Utgangspunkt hele Norge Regulerte flate tomter 20-100+ Ha Nær int. Flyplass Nær bysenter og universitet N-2 Mørk fiber >50MW tilgjengelig kraft (N-1) Infrastruktur, kjølevann, veier, etc
17
18
Konnektivitet ~284.000.000 Europeere ~20 MS To USA Norway Bergen Kårstø Oslo Trondheim Sweden Stockholm Finland Helsinki St Petersburg Kristiansand Russia Aberdeen Scotland Lista Denmark Copenhagen To USA England London Amsterdam Germany Frankfurt 19
Site: Vestfold 99 acres (40 Ha) flat site, centrally located just 15 minutes from an international airport. Abundant power is available on-site, ensuring a short time to market. Flat area 99 acres (40Ha) Substation 650 feet (200m) Available capacity 80 MW +40 MW (48 months) Highway 0,9 mile (1,4 km) International airport 8 miles (13 km) Owner Location Site accessibility & infrastructure Site area/ topography Facilitated by Statkraft. One private owner Stokke, Vestfold, Southwest of Oslo TORP Sandefjord Airport: 8 miles (13 km) City of SANDEFJORD: 11 miles (18 km) City of TØNSBERG: 10 miles (16 km) 99 Acres (40 Ha) 207 ft (63 m) above sea level Flat area Available power 80 MW + 40 MW within 24months www.statkraftdatacentersites.com Connectivity Dark Fiber Multiple providers - Routes to Stockholm, London, Amsterdam and Frankfurt Zoning Completed Q2-2018 20
Site: Telemark Flat area 190 acres (77Ha) Expandable to 1.000 acres (400Ha) Substation 0,8 mile (1,2 km) Available capacity 200 MW in 12 months +500 MW (48 months) 190 acres (77ha) of primary land located next to one of Norway s strongest power connections. The site is expandable up to 1000 acres (400ha), creating a rare European opportunity to build a large hyperscale data center park. Owner Location Site accessibility & infrastructure Site area/ topography Available power Facilitated by Statkraft. One private owner Skien, Telemark, Southwest of Oslo TORP Sandefjord Airport: 38 miles (62 km) City of SKIEN: 6,6 miles (9 km) City of PORSGRUNN: 10 miles (16 km) 1000 Acres (400 Ha) 246 ft (75 m) above sea level Flat area 200 MW in 12 months + 300 MW within 24 months www.statkraftdatacentersites.com Connectivity Dark Fiber Multiple providers - Routes to Stockholm, London, Amsterdam and Frankfurt Zoning Completed Q2-2018 21
Rød substation Rød one of Norways strongest substations 5 national 300/420 kv (blue) 6 regional 132 kv (red) Telemark Datacenter site N-3 Svelgfoss ~1 km Rød substation 22
Rød substation Rød one of Norways strongest substations 5 national 300/420 kv (blue) 6 regional 132 kv (red) Telemark Datacenter site N-3 Svelgfoss ~1 km Rød substation 23
High-voltage grids Rød Substation directly connected to one of the strongest high-voltage grids in the world Norway Sweden UK DE NL DK*4 24
Windfarms High-voltage grid connected to existing and rapidly new build wind farms Norway Sweden UK DE NL DK*4 25
Hydropower stations High-voltage grid connected to flexible hydropower stations throughout Norway Norway Sweden UK DE NL DK*4 26
Stadig bedre rammebetingelser Statsbudsjettet: 100 mill. til forbedrede fiberforbindelser til utlandet 40 mill. til forbedret kjernenett i Norge Økte rammer til Invest in Norway Fjerning eiendomsskattens verk og bruk regel («maskinskatten») NFD strategi for datasenterindustrien 27
28
THANK YOU Atle Haga Program director Mobile +47 91 37 46 19 Switchboard +47 24 06 70 00 Twitter @AtleHaga Statkraft AS Lilleakerveien 6, 0283 Oslo www.statkraftdatacentersites.com
Umulig å si hvor lang tid ting tar Facebook sin etablering i Luleå: Amazon sin etablering i Vesterås: - 2009: Besøk i Seattle - 2009: Umiddelbar respons - 2009: Besøk + RFI - 2010: Forhandlinger - 2011: Kontraktsignering - 2009: Besøk i Seattle - 2010: Første besøk i Sverige - 2011: Møteforespørsel avvist - 2012: Møte i Seattle - 2014: Besøk i Sverige + RFI - 2015, Mai: Møteforespørsel avvist - 2015, Okt.: AWS møteforespørsel - 2015, Nov. des: Møter i Seattle/Stockhom - 2016: Diverse møter - 2017, Mai: Kontraktssignering 30