Sarepta Energi AS Projects and Ambitions
A major windpower region under developement Potential:1885MW installed capasity - 5205 TWh production
Sarepta s vision The vision Is to generate values from Mid Norway wind resources The ambitions To develop and put on stream 2020 GWh new renewable energy from wind by 2020 The most cost effective in operation and maintenance of windpower in Norway
Our Ambition Realize the Fosen and Vikna wind power potential within 2020 in a joint industrial ramp up All NTE and TE wind power plants and projects integrated in «New» Sarepta AS from Joint Venture to independent wind company Amongst the most important new business in Mid-Norway for the next 20 years Attracting competent and solid partners to join us realizing the largest Norwegian wind power portfolio Create an industrial wind company with future development potential in Europe after 2020
New Sarepta - In production Valsneset, Bjugn municipality, Sør-Trøndelag: 11,5 MW Bessakerfjellet, Roan municipality, Sør-Trøndelag: 57,5 MW Hundhammerfjellet, Nærøy municipality, Nord-Trøndelag, approx. 40 MW Ytre Vikna, Vikna municipality, Nord-Trøndelag, 39,1 MW In total ~148 MW in production Corresponds to ~450 GWh/year and a income of approx. 135 MNOK annually
Sarepta s Project Portfolio Trønderenergi and NTE plan to develop and construct 800 MW wind power through Sarepta Annual production of 2,5 TWh by 2020 This portfolio consists of the largest and the most interesting projects that are realisable by the end of 2020 Capacity MW Status Ytre Vikna 1 39 In operation oct. 2012 Ytre Vikna 2 150 License granted Harbaksfjellet 91 License granted grid not developed Roan 300 License granted by NVE appealed to OED 2010 Sørmarkfjellet 150 License granted by NVE appealed to OED 2010 Frøya 60 License granted by NVE appealed to OED 2012 Skomakerfjellet 10 License granted Totalt 800 => 2,5 TWh
Projects under Development Projects announced, application for License under preparation (inland) Stokkfjellet, Selbu Municipality, Sør-Trøndelag; 100 MW Brungfjellet, Melhus og Klæbu Municipalities, Sør-Trøndelag; 150 MW Vikna Husfjellet, Vikna Municipality, Nord-Trøndelag; 9 MW
Sarepta s Ytre Vikna project, stage 1 Put on stream June and completed October 2012 39 MW installed 17 Enercon turbines per 2,3 MW Tower heights 64 and 74 m agl Annual production 120 GWh which corresponds to 7000 households Total 8,3 km roads constructed New production radial of 18 km Investment: approx. 420 mill NOK, 47 % of investment paid by Enova
Interne veier Veibygging i park ved T2, 9/8/2011
Kablellegging mot K2. (Veiparsell 2)
Dale trafo Dale trafo, 16/8/2010.
Rein på besøk like før jul..
Fundamentarbeider
Ny 132 kv linje
Turbintransport
Montasje
Sarepta Energi access the most experienced wind power competence in Norway Sarepta builds on the most experienced people in wind power production in Norway TrønderEnergi put the first commercial wind turbine in Norway in production in 1986 at Frøya NTE put the first commercial wind power plant in operation in 1991 at Vikna TrønderEnergi is benchmarked as the best in operation and maintenance of wind power plants in 2009 and 2010 (Bessakerfjellet) NTE have developed and constructed the most comprehensive demonstration wind power plant at Hundhammerfjellet based on the Scanwind technology which is procured by GE
Statnett s timeline February 2013
Timeline - scedule Utbyggingsplan Sarepta Oppdatert feb 2013 Harbaksfjellet Detaljprosjektering+anbud Utbygging Bygging infrastruktur Installasjon turbiner Idriftssettelse Sørmarkfjellet Detaljprosjektering+anbud Utbygging Bygging infrastruktur Installasjon turbiner Idriftssettelse Roan Detaljprosjektering+anbud Utbygging Bygging infrastruktur Installasjon turbiner Idriftssettelse Frøya Detaljprosjektering+anbud Utbygging Bygging infrastruktur Installasjon turbiner Idriftssettelse Ytre Vikna 2 Detaljprosjektering+anbud Utbygging Bygging infrastruktur Installasjon turbiner Idriftssettelse 2013 2014 2015 2016 2017 2018 2019 2020 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Inv.besl. Inv.besl. Inv.besl. Inv.besl. Inv.besl.
Parallell prosesses preparing for commerzialisation Finalizing projects analyzes phase 1-30.05. 2013. Legal advicors Bulding top management team Stratetic and finacial advisors