New Østfold Hospital - Kalnes
Facts New Østfold Hospital
Facts New Østfold Hospital Kalnes 82 500 m 2 gross area 3 150 user rooms 500 technical rooms 620 corridors etc. 1 000 types equipment 10 000 instances 400 types furniture 10 000 instances 2 000 types fixed furniture 15 000 instances 1 500 types HVAC/data/lab etc. 10 000 instances Costs (P50-price level february 2010) Total projectcost 5 090 MNOK incl. Equipment and VAT Contractor 2 450 MNOK exl. VAT
Facts New Østfold Hospital
Contract structure Kalnes General requirements Public roads Outdoor infrastructure - Roads, utilities, water, sewage TREATMENT BUILDING* Site clearance, excavation, filling, earth moving Structure Building envelope Foundations incl. installations BED WARD BUILDING* PSYCHIATRIC* SERVICES* Structure Building envelope Interior works incl fixed furniture Structure Building envelope Design build contracts for MEP and ICT *) Number of sections to be considered Subcontracts User equipment Outdoor finishes (atrium gardens, green roofs, helipad)
Open BIM New Østfold Hospital Sentralt styringsdokument for Prosjekt nytt østfoldsykehus Modellbasert prosjektering innebærer at BygningsInformasjonsModeller (BIM) brukes aktivt i prosjekteringsarbeidet for å oppnå bedre oppgaveforståelse, prosjektering, koordinering, kommunikasjon og kvalitetssikring i prosjektet og ikke bare til tegningsproduksjon. Det er lagt til grunn at modellbaserte verktøy tas i bruk og benyttes aktivt i alle faser av prosjektet, både når det gjelder ansattmedvirkning, prosjektering og dokument- og tegningsproduksjon.
Open BIM New Østfold Hospital Sentralt styringsdokument for Prosjekt nytt østfoldsykehus Målsettingen er at en gjennom bruk av BIM effektiviserer arbeidsprosessene, både i prosjekterings-, gjennomførings- og driftsfasen. Videre at en også etablerer en bedre basis for overlevering av FDVU-data til driftsorganisasjonen. BIM skal benyttes som basis for gjennomgang og avklaring av ulike løsningsalternativ, slik at bygningsmessige og kostnadsmessige konsekvenser raskt kan analyseres. BIM skal også benyttes som basis for grensesnittsplanlegging og kontroll.
Open BIM New Østfold Hospital Use of BIM shall contribute to achieve the project targets: Secure good information and basis for decisions Show positive and documented effects of the use of BIM and open BIM on costs, time, quality and Safety/health Facilitate for cost efficient facility management through the lifecycle of the building Carry though and document a showcase for other hospital projects Establish systematic procedures for the use of BIM and open BIM which will be of value / a learning case for other projects Forsvarsbygg 2013-05-28 8
Open BIM New Østfold Hospital Concretized: Better user process with 3D visualization Better quality design basis and documentation Energy efficient and sustainable solutions Better control with life cycle costs Industrialization of the construction Fewer errors in the construction process More efficient operation of the building Forsvarsbygg 2013-05-28 9
Adoption through challenging and facilitating
Adoption through challenging and facilitating
PNØ Model files, Arch, Struc, El. A230 Tett hus A240 Innvendig A270 Innredning B200 Råbygg E300 Elektro X200 Råbygg Kynningsrud Metacon Kynningsrud X230 Tett hus Husvik Husvik Forsvarsbygg 2013-05-28 12
PNØ Model files, Arch, Struc, El. - Ifc file sizes A230 Tett hus 8 mb 114 mb 46 mb 55 mb 2 mb A240 Innvendig 1 372 mb 83 mb 71 mb A270 Innredning 7 mb 85 mb 127 mb 26 mb B200 Råbygg 4 mb 146 mb 18 mb 7 1 mb E300 Elektro 18 mb 95 mb 42 mb 55 mb 1 mb X200 Råbygg Kynningsrud 107 mb Metacon 15 mb Kynningsrud 14 mb X230 Tett hus Forsvarsbygg 2013-05-28 13
PNØ Model files, Arch, Struc, El. - Ifc file sizes A230 Tett hus 8 mb 114 mb 46 mb 55 mb 2 mb A240 Innvendig 1 372 mb 83 mb 71 mb A270 Innredning 7 mb 85 mb 127 mb 26 mb B200 Råbygg 4 mb 1592 146 mb mb 18 mb 7 1 mb E300 Elektro 18 mb 95 mb 42 mb 55 mb 1 mb X200 Råbygg Kynningsrud 107 mb Metacon 15 mb Kynningsrud 14 mb X230 Tett hus Forsvarsbygg 2013-05-28 14
PNØ Model files HVAC, Plumb. V300 Vann, avløp, varme V300 Kulvert U2 V311 Bunnlednin g V330 Sprinkler V340 Gass & trykkluft V360 Luftbehandling V360 Luftbehandling 4.-5. etasje Eleiko Forsvarsbygg 2013-05-28 15
PNØ Model files HVAC, Plumb. - Ifc file sizes V300 Vann, avløp, varme 156 mb 63 333 mb 19 V300 Kulvert U2 12 mb 11 mb 12 mb 12 mb V311 Bunnlednin g 4 mb 17 mb 13 mb 14 mb V330 Sprinkler 138 mb 112 mb 36 mb V340 Gass & trykkluft 85 mb 4 V360 Luftbehandling V360 Luftbehandling 4.-5. etasje Eleiko 12 mb 494 mb 612 mb 161 mb Forsvarsbygg 2013-05-28 16
PNØ Model files HVAC, Plumb. - Ifc file sizes V300 Vann, avløp, varme 156 mb 63 333 mb 19 V300 Kulvert U2 12 mb 11 mb 12 mb 12 mb V311 Bunnlednin g 4 mb 17 mb 13 mb 14 mb V330 Sprinkler 3094 138 mb mb 112 mb 36 mb V340 Gass & trykkluft 85 mb 4 V360 Luftbehandling V360 Luftbehandling 4.-5. etasje Eleiko 12 mb 494 mb 612 mb 161 mb Forsvarsbygg 2013-05-28 17
PNØ Model files - Ifc file sizes all model files V300 Vann, avløp, varme 156 mb 63 333 mb 19 V300 Kulvert U2 12 mb 11 mb 12 mb 12 mb V311 Bunnlednin g 4 mb 17 mb 13 mb 14 mb V330 Sprinkler V340 Gass & trykkluft 4686 3094 138 mb mb 112 85 mb 4 36 mb V360 Luftbehandling V360 Luftbehandling 4.-5. etasje Eleiko 12 mb 494 mb 612 mb 161 mb 231 mb 2 294 mb 1 614 mb 543 mb 4 mb Forsvarsbygg 2013-05-28 18
From individual and fragmented, to shared and standardized data Building application E-submission -Local authority -Building permit Knowledge databases -Best practice -Specific knowledge Briefing, requirements -Functions -Estimates, -Budget -Requirements Renovation, rehabilitation -Renovation -Demolishing -Rehabilitation IFC Building Information Model (BIM) CAD software -Drawings, calculations -Architect, engineer, Simulations -Indoor climate -Ventilation, HVAC -LCCA -Light and acoustics -Heat loss -Fire -Environmental impact FM Operation -Leasing, sale -Maintenance -Guarantees Progress - time schedules -Progress planning -Logistics, 4D Building specifications -NS 3420 -NS 3451 -Calculations, budget Tendering -Product databases -Price databases Forsvarsbygg 2013-05-28 19 19
From individual and fragmented, to shared and standardized data Building application E-submission -Local authority -Building permit Knowledge databases -Best practice -Specific knowledge Briefing, requirements -Functions -Estimates, -Budget -Requirements Renovation, rehabilitation -Renovation -Demolishing -Rehabilitation ID M IFC Building Information Model (BIM) CAD software -Drawings, calculations -Architect, engineer, Simulations -Indoor climate -Ventilation, HVAC -LCCA -Light and acoustics -Heat loss -Fire -Environmental impact FM Operation -Leasing, sale -Maintenance -Guarantees Progress - time schedules -Progress planning -Logistics, 4D Building specifications -NS 3420 -NS 3451 -Calculations, budget Tendering -Product databases -Price databases Forsvarsbygg 2013-05-28 20 20
From individual and fragmented, to shared and standardized data Building application E-submission -Local authority -Building permit Knowledge databases -Best practice -Specific knowledge Briefing, requirements -Functions -Estimates, -Budget -Requirements Renovation, rehabilitation -Renovation -Demolishing -Rehabilitation ID M IFC Building Information Model (BIM) CAD software -Drawings, calculations -Architect, engineer, Simulations -Indoor climate -Ventilation, HVAC -LCCA -Light and acoustics -Heat loss -Fire -Environmental impact FM Operation -Leasing, sale -Maintenance -Guarantees Progress - time schedules -Progress planning -Logistics, 4D Building specifications -NS 3420 -NS 3451 -Calculations, budget Tendering -Product databases -Price databases 21
Model maintenance through the construction phase Control Design team: Virtual construction site Main contractor 3 Main contractor.. 2... Main contractor 1.. Input for detail design Shop drawings Sub contractor b1 Sub contractor b2 Sub contractor b3 Client Struc ARCH BIM Mech Model and harvest from model Working drawing Basis for shop drawings IFC, Solibri, Navisworks, FM SØ users RIn El Design (ARCH + STRUC) Modelling (Design team) Coordination (Design team + DB contractor + Main contractor) Design build contractor 2 Design build contractor 1 System design Basis system design Shop drawings Sub contractor t1 Sub contractor t2 Sub contractor t3 22
23
Experiences Challenges Handling of large models, both in BIM authoring software and in downstream applications The information part, use of name, description, property sets etc. Different exports do this differently Organization of a large number of model files will be even worse through life cycle Duplicates, same object designed by different disciplines Moving on site Forsvarsbygg 2013-05-28 24